Historic Barzan Gas Project’s Train 1 more than 95% complete | Historic Barzan Gas Project’s Train 1 more than 95% complete -
The construction of the $10.3 Barzan Gas Project, which includes both offshore and onshore facilities, started in 2011. The offshore facilities include three offshore wellhead platforms, subsea pipelines and cables.

Historic Barzan Gas Project’s Train 1 more than 95% complete

: Thursday, September 04 - 2014 @ 14:04

RasGas Company Limited (RasGas) announced that Train 1 of its historic Barzan Gas Project (BGP), which will play a significant role in meeting Qatar’s rapidly growing domestic energy demand, is more than 95% complete and is rapidly ramping up for first production of clean-burning natural gas in the first quarter of 2015.

Construction work on Train 2 is also progressing well with expectations to be completed by the middle of 2015. Once completed, the two processing trains will produce around 1.4 billion standard cubic feet a day (bcfd) of sales gas.

Combined with RasGas’ other facilities production (LNG and sales gas), the BGP is set to make RasGas one of the largest single gas processors in the world with a production capacity of 11 bcfd (the equivalent of almost two million barrels of oil). In addition to sales gas, Barzan will produce about 22,000 barrels per day (bpd) of field condensate, 6,000 bpd of plant condensate, 34,000 bpd of ethane, 10,500 bpd of propane and 7,500 bpd of butane.

His Excellency Dr. Mohammed bin Saleh Al-Sada, Minister of Energy and Industry, said, “The Barzan Gas Project is strategically important for Qatar’s sustainable economic development, and is a powerful step forward in the country’s overall industrial and human development, in line with Qatar National Vision 2030, under the wise leadership of His Highness Sheikh Tamim bin Hamad Al Thani, the Emir of the State of Qatar, carrying on the vision of His Highness the Father Emir Sheikh Hamad bin Khalifa Al Thani. I would like to commend RasGas, its shareholders, Qatar Petroleum and ExxonMobil Corporation, its contractors and all involved in this massive project for their commitment, outstanding management and world-class safety achievements.”

The construction of this mega-project, which includes both offshore and onshore facilities, started in 2011. The offshore facilities include three offshore wellhead platforms, subsea pipelines and cables. The onshore facilities are comprised of a gas processing unit, a sulphur recovery unit to remove impurities from the natural gas, and a natural gas liquids (NGL) recovery unit, which will produce methane, ethane, propane, butane and condensate. Ethane produced from the plant will be used as a feedstock for the growing Qatari petrochemical industry. RasGas was appointed by its shareholders, Qatar Petroleum and ExxonMobil, to design, construct and operate the BGP, which is one of the largest and most technologically advanced gas projects in the region.

Safety Performance
The project has maintained world-class safety performance and industry-leading results for the last three years through a disciplined approach to process safety and relentless focus on accident prevention and continually improving project execution practices.

Emphasising the need for continued vigilance, Hamad Rashid Al Mohannadi, RasGas’ Chief Executive Officer, said, “The Barzan Gas Project is a prime example of RasGas’ commitment to safety and excellence in project management and execution. I am proud to note that we have already achieved an unprecedented world-class safety record of 130 million man-hours without a lost time incident (LTI). I would like to thank our shareholders, contractors, employees and workers for this outstanding achievement given the complexity of managing a multi-national workforce of more than 30,000 people at peak construction in very challenging conditions.”

Environmental Commitment
Al Mohannadi also cited the company’s commitment to the environment as a high priority area where RasGas has taken significant strides in ensuring that the BGP facilities are built utilising the right technology and sound engineering design to operate safely and reliably.

Various innovative technologies and controls are being implemented to minimise adverse environmental impacts. These include using the best available technology (BAT) for combustion sources, utilising innovative start-up flare minimisation strategies, and undertaking environmental projects to protect coral and marine life. The facility will also utilise ExxonMobil’s Flexsorb® SE Plus for tail gas treatment of the sulfur recovery plant which will allow the facility to achieve 99.4% recovery efficiency, which will be the highest recovery efficiency of any gas treatment project in Ras Laffan Industrial City. Specialised burner technology has also been installed on fired equipment and gas turbines to help minimise nitrogen oxide (NOx) emissions.

As part of RasGas’ efforts to preserve marine life and protect biodiversity in its project waters, the company relocated around 1,600 corals living along the Barzan Gas’ pipeline route prior to construction. This was done in consultation with Qatar’s Ministry of Environment.

Qatarization Achievements
Another first that distinguishes the project is the number of Qatari nationals working on the project. The Barzan Gas Project has the highest number of Qataris, working in almost every key discipline, of any single RasGas project, thus ensuring that maximum exposure and experience are given to national graduates to develop their career in the Qatari energy industry. This included embedding them with the project teams in Japan and South Korea throughout the different phases of the project. Additionally, a broad range of Qatari companies have also been involved in providing essential support in terms of manpower, materials, equipment and services.

Contractors and Customers
Several contractors played a key role in the planning, engineering, procurement, construction and development of the project including JGC Corporation and its sub-contractors for the onshore facilities and Hyundai Heavy Industries for the offshore facilities. Yet another key feature of this major “from Qatar to Qatar” project has been the utilisation of a large percentage of Qatari sub-contractors, further developing national capability.

Once completed, a major portion of the Barzan gas production will be used by the power and water generation sectors, enabling them to utilise clean-burning natural gas to support several of Qatar’s new projects that are underway.

For more info please contact:
Yosra Koura
Media Relations Officer
Tel: +97444531130
Tel: +97433446448
[email protected]

Today's Top Stories

Posted by

Thursday, September 4- 2014 @ 14:04 UAE local time (GMT+4) Replication or redistribution in whole or in part is expressly prohibited without the prior written consent of Mediaquest FZ LLC.

AME Info Services







Business DirectoryVIEW ALL

Search by name

Search by industry

Browse alphabetically





JobsVIEW ALL

Search for jobs

Latest Jobs