First shipment of LNG from the Gorgon Project departed Barrow Island off the North West coast of Western Australia. Source: Chevron website

* Gorgon LNG train 1 resumes operation: spokesman

* Asian spot LNG prices at near 2-year high

Chevron Corp said on Wednesday it has resumed production of liquefied natural gas (LNG) at one of its two units at the $54 billion Gorgon project, located off Western Australia, after an outage of slightly more than a month.

“Gorgon LNG Train 1 operation resumed earlier this week,” a spokesman for Chevron wrote in an emailed statement. “Production was halted in late November 2016 to assess and address some performance variations,” the statement said, without disclosing details of the “variations”.

Output unaffected

Output at the plant’s train 2 production line was unaffected during the period, the spokesman said. The Gorgon project had continued to produce and load cargoes, he said.

The massive Gorgon project has been plagued by a string of operational issues since it started up in March 2016.

Despite the continued production form the second train, the supply disruption led to an urgent demand for replacement cargoes to fulfil customer commitments, according to traders familiar with the matter.

That helped spot LNG prices for delivery to North Asia rise to near two-year highs of $9.50 per million British thermal units (mmBtu) last week, their highest level since early 2015, compared with spot levels around $7/mmBtu before news of the Gorgon train 1 outage broke in late November.